ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PROYEK PEMBANGUNAN GEDUNG KANTOR PT. PRIMA INDOJAYA MANDIRI
Sari
From the results of this research, the average field productivity value was 4.41 m³/person for foundation work, 4.54 m³/person for casting work, 1,017.46 kg/person for iron work, and 14.32 m²/person for formwork work. The productivity value according to SNI is 0.938 m³/person for foundation work, 4 m³/person for casting work, 200 kg/person for steel work, and 4.24 m²/person for formwork work. Then the productivity value according to the PUPR Ministerial Decree is 0.67 m³/person for foundation work, 4 m³/person for casting work, 71.46 kg/person for steel work, 9.09 m²/person for formwork work. There are quite significant differences for all jobs when compared with the reference (SNI 7394-2008 and PUPR Ministerial Regulation 28-2016). In foundation work, the comparison of field productivity with SNI is 4.71 times and with the PUPR Ministerial Regulation is
6.58 times. In casting work, field productivity with SNI and PUPR Ministerial Regulations is the same, namely 1.135 times. In steel work, the comparison of field productivity with SNI is 5.09 times and with the PUPR Ministerial Regulation is 14.24 times. In formwork work, the comparison of field productivity with SNI is 3.38 times and with the PUPR Ministerial Regulation is 1.58 times..
Keywords: Labor Productivity, PermenPUPR, Indonesian National Standards
Teks Lengkap:
PDFReferensi
Agnese Therese Lagonda1), Pingkan A.K Pratasis2), Jermias Tjakra3). Analisis Penerapan Produktivitas tenaga kerja Pada Proyek Konstruksi
Ardani1), Syahrizal2), Alferido Malik3). 2010. Analisa Penerapan Produktivitas tenaga kerja Pada Proyek Konstruksi. Sumatra Utara
Fiki Aryani1), Rafie2), Syahruddin3). Analisa Penerapan Produktivitas tenaga kerja Pada Proyek Konstruksi Jalan Lingkungan Lokasi Kalimantan Barat
Hariandja1), Marihot Tua Efendi2). 2002. Manajemen Sumber Daya Manusia, Grasindo, Jakarta.
Mumtaz Almukaffa Ayatullah1) , Anik Sarmingsih2), Syafrudin3). Analisis Produktivitas tenaga kerja Pada Proyek Pembangunan Jalan Parang Garuda East Kawasan Industri Kendal
PermenPUPR28-2016.
Ronny Walangitan. (2012). Produktivitas Tenaga Kerja Dengan Menggunakan Metode Work sampling Pada Pekerjaan Kolom dan Balok Mega Trade Center Manado.
SNI 7394-2008.
Syahreza Taruna. 2015. Analisa Penerapan Produktivitas tenaga kerja Pada
Proyek Pembangunan Gedung Pendidikan Terpadu Politeknik Negeri Manado. Manado
DOI: https://doi.org/10.33559/eoj.v7i1.2653
Refbacks
- Saat ini tidak ada refbacks.
Negara Pengunjung

Ciptaan disebarluaskan di bawah Lisensi Creative Commons Atribusi 4.0 Internasional.